Statistical or Overview Information
Start Date: February 2015
Completion Date: October 2015
Wanzek was the EPC contractor for Briscoe, a 150 MW project consisting of 81 GE 1.85 MW turbines. This project included a 34.5:115 kV step-up substation with a single transformer bay, six open air collection feeder circuits and a single step 34.5 kV 15MVAR capacitor bank.
Project Scope: | |
---|---|
|
|
Location Briscoe, TX