Canadian Breaks

Canadian Breaks Masthead_121322
sprite-7

Statistical or Overview Information

Start Date: July 2018

Completion Date: October 2019

Canadian Breaks was a 200 MW wind project that was completed on schedule, had over 200,000 man hours and zero recordable injuries. The team battled through many weather challenges, including a few 90 mph wind events, extreme flooding and more. Despite difficulties posed by nature, the Canadian Breaks team pulled through to complete this successful project.

Project Scope:

  • Construction of O&M building
  • Foundation, turbine, collection, substation and transmission line installation
  • Full civil work
  • Full EPC contract of the installation of 87 each 2.3 MW Siemens turbines

Location Vega, TX