Statistical or Overview Information
Start Date: August 2015
Completion Date: March 2017
Wanzek Construction, Inc. was hired as an EPC contractor to complete the construction of the Courtenay Wind Farm project. The 200 MW project consisted of 100 Vestas turbines enough to power approximately 105,000 homes. The scope included the construction of all necessary roads, collection system, substation, transmission line and erection activities.
Project Scope:
- Collection system installation
- Heavy/civil road
- Installation
- Substation
- Transmission line
Location Courtenay, ND