Statistical or Overview Information
Start Date: June 2018
Completion Date: November 2018
The Foxtail Wind Farm was one of the four-pack of projects for the client that Wanzek constructed over the course of two years. Foxtail was the smallest of the four-pack projects, consisting of 75 each 2.0 MW Vestas machines combining for a total of 150 MW, enough energy to supply approximately 50,000 homes.
Project Scope:
- Civil
- Foundation installation
- Underground collection system installation
- Construction of the 34.5 kVA substation and tie in to the Ottertail Power substation
Location Kulm, ND
Project Profile Download