Statistical or Overview Information
Start Date: June 2018
Completion Date: November 2019
Through changing site conditions, extreme winter weather and more, the Wanzek team successfully erected this wind farm. Hubbard was an EPC project consisting of 99 GE 2.82 MW WTGs with a 114-meter hub height and 9 GE 2.32 MW WTGs with an 80-meter hub height. The 108 WTGs combine for a total output capacity of just over 300 MW. Hubbard also executed 108 main crane break downs through the course of completion.
Location Waco, TX
Project Profile Download
Project Scope
Self-Perform
- Roads
- Foundations
- Turbine offload
- Erection
- Mechanical completion
- Tower wiring
- Collection system
- Terminations
- Collection system trenching
- Meteorological tower install
- Concrete
- Aggregate
- Material testing