Statistical or Overview Information
Start Date: May 2023
Completion Date: April 2024 (Projected)
Rice Creek Solar Project is located on two parcels of land in northeast Florida near Putnam County. The project will consist of over 225,000 solar panels producing nearly 100 MWdc and 75 MWac power to over 15,000 homes.
Location Palatka, FL
Project Profile Download
Project Scope
Self-Perform
- Procurement of all major equipment, racking material and modules provided by client
- Site grading, civil construction and road/SWPPP install
- Pile and single-axis tracker installation
- MV, DC and fiber optic cable install
- Module installation and wire management
- Commissioning and testing
- Substation construction
Subcontractors
- Design
- Substation foundations, sitewide permanent fence, clearing and grubbing
- Substation testing
- O&M building
- AC cable plowing, fiber terminations and testing
- Material testing
- Security cameras
- Aggregate supply
Inverters
- 75 MWac, 97 MWdc