Statistical or Overview Information

Start Date: July 2022

Completion Date: December 2023

Storey Solar is located in Pinal County, Arizona on a property size of 748 acres. Onsite there are 40,849 piles, 301,636 modules and 2,742 tracker rows.

Location Coolidge, AZ

Project Profile Download

sprite-4

Project Scope

Self-Perform
  • Civil site grading (including substation and BESS pads, roads and SWPPP measures)
  • Pile installation
  • Tracker installation
  • DC cable and grounding cable installation
  • Module installation
  • Wire management
  • Commissioning and testing
Subcontractors
  • MV cable
  • Perimeter site fence
  • Pile boring subcontractor
  • Temporary power installation
  • Third-party testing
  • Thermal grouting
Inverters
  • 30 Power Electronics
  • 88 MWac, 169 MWdc