Statistical or Overview Information
Start Date: April 2022
Completion Date: June 2023
The Sunflower Wind Farm is a 214 MW power plant designed and built by Wanzek Construction, Inc. consisting of 76 GE 2.82 MW turbines. Nearly 20 miles of access roads were installed, over 70,000 CY of concrete poured and almost 500 tons of rebar tied. Over 225,000 LF of MV cable was trenched/installed across the eight circuits on the project footprint. Thus far, all scopes have been completed safely with the utmost quality and on time with respect to the baseline schedule agreed to with the client. By upholding our beliefs, the Wanzek management team was able to successfully foster positive relationships with our client, the OEM, subcontractors, vendors and various representatives within the local community.
Location Peabody, KS
Project Profile Download
Project Scope
EPC
- Offload
- WTG erection
- Tower wiring
- O&M building
- ADLS
- MV cable
- Design
- Material testing
- Cement stabilization
- Aggregate
- Access roads
- Excavation/backfill
- Blasting
- Geopiers
- Rebar and concrete
- Boring
- Trenching
- Terminations