Statistical or Overview Information
Start Date: June 2015
End Date: October 2015
Wanzek was the EPC contractor for the Thunder Spirit Wind Project, located in Hettinger, North Dakota. The project included a 34.5:230kV step-up substation with a single transformer bay and six open-air collection feeder circuits.
Project Scope:
- Control terminations and testing
- EPC services
- Equipment installation
- Foundations
- Relay installation and settings
- Steel erection
Location Hettinger, ND
Project Profile Download