Statistical or Overview Information

Start Date: August 2019

Completion Date: November 2020

The Triple H Wind Farm was completed ahead of schedule, took over 270,000 man hours, accomplished with zero reworks and a satisfied client all while enduring the highest rainfall amounts in 20 years amid a pandemic. The project is developed and owned by the client with subsequent phases already planning to be constructed. Triple H is located in Hyde County just outside of Highmore, South Dakota on 35,000 acres of 60% tillable/40% pasture land. The installation consists of 92 turbines creating up to 250 MW of power.

Project Scope:
  • ADLS install
  • Civil construction
  • Design for all scopes
  • Foundation construction
  • Meteorological tower install
  • Substation construction
  • WTG installation
  • 5,500 SF O&M building
  • 92 GE 2.72 MW WTGs
  • Underground collection system installation



Location Highmore, SD

Project Profile Download

sprite-4

Image Slider

Triple H 07302020-008
Triple H 07302020-044
Triple H 07302020-162
1
3
sprite-7
Wind CTA_121222

Be part of something big.

sprite-6