Statistical or Overview Information
Started: March 2020
Completed: March 2021
This is the first of three projects in Florida awarded by the client. The project is a 75 MW site, with 20 TMEIC Ninja Inverters, 234,920 modules, 2,816 mechanical racks and 31,844 piles. The majority of the project was constructed using self-perform methodology (few subcontractors). Twin Rivers was the first EPC lump sum solar project built by Wanzek for the client.
Project Scope:
- Site grading
- Civil construction including rough grading of substation area
- Roads
- Pile installation
- Single-axis tracker installation
- MV and DC cable installation
- Fiber optic cable installation
- Module installation
- Wire management
- Commissioning and testing
Location Lake City, FL