Rockland Wind Farm - 79.2MW

Wanzek Construction crews are currently on site at the 79.2MW Rockland Wind Farm, a Ridgeline Energy project. The site, which will employ 44 Vestas V100 1.8MW turbines, began construction in early 2011 and will continue through September. For the American Falls, Idaho project, Wanzek was able to draw on a large local hiring pool for labor resources, resulting in approximately 50% of employees on site being from the American Falls community and surrounding area. Wanzek's scope of work includes Sitework and Roads, Foundations, an O&M Building, Substation, Transmission Lines, Underground Collection and Turbine Erection.