Wanzek Construction broke ground in November of 2009 as the Cedro Hill BOP contractor erecting 100 GE 1.5MW turbines. Wanzek is handling all civil work, foundations, erection, overhead and underground collection systems, and substation O&M building.
 
Cedro Hill Wind Farm was completed in March of 2010.