Crofton Bluffs Wind Project

Wanzek is the Balance of Plant Contractor and is responsible for engineering, civil construction, turbine erection, collection system installation, substation installation and the construction of an Operations and Maintenance Building.  Just started O&M construction in April 2012.  Civil, collection, substation work all set to begin in June 2012.  Turbine erection starts in August.  Project completed October 2012.